"It is actually open right now." That's what Orange County Parks Commissioner Travis Ewald told the county legislature's Physical Services Committee on May 26, 2026, according to the meeting minutes. A legislator had asked whether people would get a place to park at Camp LaGuardia and walk onto the Heritage Trail. Ewald said they already had one.
The county plans to turn its 258-acre property off Greycourt Road into a major park. The first public piece is the lot that serves a trail that already runs past the property. That order follows the plan itself. The future park is designed around the spot where two trails meet: the Heritage Trail and the Schunnemunk Rail Trail. The county is building outward from that junction.
Inside the Main Gate, Down to the Left
Ewald's directions to the committee were simple. Go in the main gate and head down to the left. There's a small parking area there with direct access to the Heritage Trail.
Beyond that lot, most of the 258 acres is still a demolition and cleanup site. County crews handled much of the demolition themselves to save money, News 12 Hudson Valley reported on October 15. Some stone from the old buildings will be crushed and reused for future foundations. In May, Ewald said one smaller building near the Heritage Trail was still standing and expected to come down. The county was also seeking proposals on whether to rehab the large maintenance garage or build a new one. He said the rest of the year would go to clearing debris.
The Heritage Trail itself is the long-running paved route through Chester, Goshen and Monroe. The Open Space Institute described it as 20 miles long in a June 2026 release. Anyone already riding or walking it has a new place to start.
Why the Trail Junction Comes First
Most of the park plan follows from one fact. Camp LaGuardia sits at the end of an abandoned railbed. The Schunnemunk Rail Trail is a planned 10-mile multi-use path on the old Erie Railroad Newburgh Branch, the former Erie–Lackawanna corridor. It will run from the base of the Moodna Trestle in Cornwall, through Blooming Grove and the Village of Washingtonville, to Camp LaGuardia. That's where it meets the Heritage Trail.
The Open Space Institute bought nearly ten miles of the unused corridor in 2021 and sold the railbed to the county in 2024. The Warwick Advertiser reported at the time of that transfer that the trail is meant to link Schunnemunk Mountain State Park and Goosepond Mountain State Park. It would also connect to the Salisbury Mills–Cornwall and Harriman train stations.
The county's July 2025 master plan treats that junction as the park's front door. It calls for a "Heritage Station" with parking, restrooms, trail-oriented retail, a gathering space and bike share. The rail trail is designed differently from the Heritage Trail:
| Feature | What the master plan specifies |
|---|---|
| Length | 10 miles, Moodna Trestle to Camp LaGuardia |
| Width | 16 feet paved, narrowing to 12 feet in less urban areas |
| Layout | Two 5-foot bike lanes plus a 6-foot pedestrian path |
| Cost | About $28 million |
| Funding | 80% federal through FTA Section 5307, 10% NYSDOT, 10% Orange County |
The plan calls this the county's first split-use rail trail, with bikes and pedestrians in separate lanes.
One piece of the junction is still missing. Norfolk Southern owns the railbed's wye junction near Camp LaGuardia, the triangle of track that would connect the two trails directly. Until the county acquires it, the plan calls for an interim multi-use path through the park's eastern uplands. Ewald described a similar route in May. The Schunnemunk Trail would run alongside the open parking area and use lower Camp LaGuardia Road to reach the rail corridor.
There's also a small piece of new infrastructure at the site already. The Open Space Institute said West Point cadets completed a 26-foot bridge over Seely Brook in 2026, working with the county, to improve trail access at the future park.
How the Rail Trail Schedule Moved This Year
With the junction still unbuilt, there isn't much else to use yet. Over the past 16 months, the county's public statements about the rail trail have moved steadily later.
- July 2025. The master plan said detailed design was scheduled for 2025, with construction expected in 2025–2026.
- August 2025. A county account reported by The Chronicle listed construction of the first two-mile phase as recent progress.
- April 2026. The Times Herald-Record reported that a 2-mile Phase 1 stretch from Camp LaGuardia to Craigville Road was under construction. Citing the office of county Planning Director Alan Sorensen, it said the stretch was expected to be finished in fall 2026.
- May 2026. Ewald told the committee the county planned to open the Schunnemunk Trail later in the year. He said Public Works had graded about a mile and a half of Craigville Road.
- October 2026. County spokesperson Rebecca Sheehan told the Warwick Advertiser, "The construction of the rail trail and the first phase projects is expected to start in late 2027 or early 2028."
The most recent county statement puts construction of the funded $28 million trail and the first park amenities on the same start date, late 2027 or early 2028. Sheehan said funding for the rail trail is secured. The county will keep applying for federal and state grants for later park improvements.
What the Playground Money Buys
The park's first named pieces were funded this fall. Orange County won a $2.5 million NY PLAYS state grant for playgrounds and restrooms. The county's application put that part of the project at $3.125 million, including a $625,000 local match, News 12 reported. In May, Ewald said phase one would add three parking areas: one for the dog park, an expanded lot by the Heritage Trail, and one by the playground. The lot open now is the one set to grow.
The full master plan lists much more:
- A flex sports field, seven pickleball courts and basketball
- Playgrounds and a small splash park
- A dog park
- Pavilions, a stage and picnic areas
- Nature trails, information kiosks and a bird blind in the western lowlands
- Fishing access on Seely Brook
- A Spanish Terrace overlook
- 41 campsites, a mix of RV, cabin or platform, and tent sites
Sheehan said the park will be free to enter. Only the campgrounds will charge a fee. County Executive Steve Neuhaus told News 12 the first phase could be ready as early as 2027, with full development taking about five years. The July 2025 master plan sets a longer window for building out everything on its list, 10 to 20 years, with costs reaching into the tens of millions. It says the order of projects depends on funding and staffing and can be reshuffled.
On roads, the plan describes access from Route 17 via Greycourt Road, Lehigh Avenue or Craigville Road. Chester Dial-a-Ride and the trails also reach the site.
What Stays on the Property
The county bought Camp LaGuardia in 2007 for $8.5 million. The site was first a women's prison and later a shelter for homeless men from New York City. Neuhaus told News 12 that past redevelopment proposals included multifamily housing. Local and county officials didn't think that fit, and a park won support from the surrounding municipalities and the County Legislature.
The site goes back further than the prison. One of its early owners was Elihu Marvin, a Revolutionary War officer. The Marvin family cemetery, with graves from that era, is listed on the National Register of Historic Places. It will stay on site for visitors to see. The master plan's mission statement says the park "will draw inspiration from its historical character."
Most of the land sits in the Town of Chester, but the project belongs to the county. Town Supervisor Brandon Holdridge told the Warwick Advertiser the town isn't involved because it's county property. "It all sounds great," he said. He added that he expects it would be good for the area and the local economy. For updates on the trail, check the county's Schunnemunk Rail Trail project page.
A new park, a dog park and a trail junction off Greycourt Road could change how buyers see the streets around them over the next few years. If you own a home near Camp LaGuardia or along the Heritage Trail and want to know where your value stands today, James J Cosenza can walk you through it. Request your free home valuation.